Town of Greenville Ten-Year Road Improvement Plan
Revised June 1, 2005 by Road Commissioner John Simko and Public Works Foreman Mike Thornton

The purpose of this document is to illustrate the plan for road improvement over the next ten years, and to also demonstrate that currently-available funds are insufficient to meet the Town's road improvement needs. It should be noted that this plan does not include any funds for new sidewalk construction nor sidewalk maintenance. It also does not pay for parking lot improvements. It does utilize estimates by the authors based on the cost experience for road paving and improvement over the past four years. It assumes the Town will only utilize the $27,000 provided annually by the MDOT for local road improvement through the Rural Road Initiative (unless otherwise noted).

2004
Overlay Dorr Street $8,000
Overlay Spruce Street to RR tracks $8,000
Shim and overlay Spruce Street – RR Tracks to MSD $5,000
Shim and overlay South Maple Street – Pritham to Brook St. $6,000
TOTAL $27,000


2005

WITHOUT ADDITIONAL RESOURCES
Grind out a short section of Cemetery Lane and resurface: shim and overlay rest of Cemetery Lane and also Franklin Place. Shim and overlay north side of Eveleth Hill, extending to south side as far as possible.
Estimated Total: $27,000

WITH ROAD IMPROVEMENT BOND TO COMPLETE ALL OF VARNEY AND SCAMMON ROADS, CEMTARY LANE AND FRANKLIN PLACE
Reclaim and grade the pavement on Scammon Road (excluding 500' section already reclaimed); reclaim, grade, and add geotextile fabric to Scammon Road from knoll east of the snowmobile clubhouse to the end of the pavement, and south on Varney Road to the knoll by Morrison's; add 12” of gravel to these reclaimed surfaces; apply bituminous asphalt 1 1/2 ” binder and 1” overlay; shim and overlay Varney Road from Airport Access Road to knoll north of Morrison's.
(late summer 2005 / early summer 2006)

Grind out a short section of Cemetery Lane and resurface: shim and overlay rest of Cemetery Lane and also Franklin Place.
(late summer 2005) ~ $374,134

Shim and overlay north side of Eveleth Hill, extending to south side as far as possible.
(early summer 2005) ~ $3,546

Shim and overlay all of Leisure Life Road
(late summer 2005) ~ $16,180

Grade, add geotextile fabric, and add 8” – 12” of screened gravel to part of the Walden Farm Road – 650' from end of pavement at intersection of Varney Road. ~$8,140

(NOTE: as part of summer roads maintenance budget, will apply surface gravel to North Birch Street and East Road and grade as necessary.)

TOTAL FOR WORK BEYOND BOND PROCEEDS: $27,866

TOTAL ALL WORK LISTED for 2005 (or spring 2006): $402,000

(Total for bond proceeds and state local road assistance money = $402,000)

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS ARE COMPLETE


2006

Install underground drainage, curbing, and consider sidewalk along Eveleth Hill from Moosehead Lake Road to top of hill; shim and overlay surface. ~ $27,000

IF VARNEY, SCAMMON, AND LEISURE LIFE ROADS INCOMPLETE

Shim and overlay Leisure Life Road ~ $18,000

Shim and overlay Eveleth Hill Road from Moosehead Lake Road to top of hill ~ $9,000

TOTAL: $27,000


2007

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS ARE COMPLETE

Shim and Overlay Pine Street ~ $11,000

Shim and overlay 1/3 mile of Crafts Road from Pritham Avenue ~ $16,000

TOTAL: $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Grind, grade, and add 8” to 12” of gravel to first 1,000' of Scammon Road ~ $27,000

IF WE PARTICIPATE IN RURAL ROAD INITIATIVE FOR DREW ROAD

Pay 1/3 of total cost for grinding, grading, and resurfacing Drew Road ~ $61,000
(should be raised separately or refinance road bond to include this new cost)


2008

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay all of Mayhew Manor Road (Eveleth to Spruce) ~ $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Apply binder and overlay to 1,000' of Scammon Road ~ $12,000

Overlay Oliver Road ~ $15,000

TOTAL: $27,000

IF WE PARTICIPATE IN RURAL ROAD INITITATIVE FOR EAST ROAD

Pay 1/3 of total cost for grinding, grading and resurfacing parts of East Road ~ $91,000
(consider refinancing road bond to include this new cost)


2009

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay Sherwood Avenue and Crescent Street ~ $17,000

Shim and overlay Murray Street to Dean Park ~ $10,000

TOTAL: $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE Grind, grade, and add 8” to 12” of gravel next 1,000' of Scammon Road ~ $27,000


2010

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay Oliver Road ~ $17,000

Overlay Lewis Road ~ $10,000

TOTAL: $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Resurface second 1,000' of Scammon Road with binder and overlay ~ $14,000

Shim and overlay Murray Street ~ $13,000

TOTAL: $27,000


2011

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay both ends of Shaw Street ~ $18,000

Shim Prospect street ~ $9,000

TOTAL: $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Grind, grade and add 8”-12” of screened gravel to 1,000' of Scammon Road ~ $27,000
(Gagne's residence to lower driveway of snowmobile clubhouse)


2012

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay Foss Street – fix underground drainage if undone ~ $12,000

Shim and overlay South Wiggins Street ~ $15,000

TOTAL: $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Resurface 1,000' with binder and overlay on Scammon Road ~ $15,000

Shim and overlay rest of Scammon Road (to end of pavement at Varney Rd. intersection) and shim and overlay 5-mile crack on Varney Road ~ $12,000

TOTAL: $27,000


2013

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay remainder of Crafts Road ~ $20,000

Shim and overlay Doan Street (and pave plow turn-around if necessary) ~ $7,000

TOTAL: $27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Shim remainder of Varney Road ~ $27,000


2014

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and overlay south end of South Maple Street ~ $13,000

Shim and overlay Depot Street to Industrial Park entrance* ~ $14,000
(*assuming cost-share with Piscataquis County, possibly Industrial Park users)

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Overlay Varney Road ~ $14,000

Shim and overlay south end of South Maple Street ~ $13,000

TOTAL: $27,000


2015

ASSUMING VARNEY, SCAMMON AND LEISURE LIFE ROADS COMPLETE

Shim and Overlay Washington Street ~ 27,000

IF VARNEY AND SCAMMON ROADS INCOMPLETE

Shim and overlay Scammon Road from Larsen's to Gagne's (crest of hill) ~ $18,000

Shim and overlay School Street ~ $9,000

TOTAL: $27,000


This schedule does not account for any work for a ten year period on the following paved streets which currently require work (list will grow over time):

  • Lincoln (upper and lower)
  • Village Street
  • Cottage Street
  • Norris Street
  • Minden Street
  • Lakeview Street
  • Cross Street
  • High Street
  • Hospital Street
  • South Birch Street
  • North Birch Street
  • McAfee Street
  • North Maple Street
  • South Doan Street
  • Upper end of Spruce Street
  • Carpenter Place